
Reflecting on President Trump’s first 100 days in office
Energy and infrastructure projects often span decades, involve substantial capital investment, and operate in politically sensitive environments. One of the most significant challenges these projects face is political risk–uncertainty stemming from governmental or policy changes that can disrupt, delay, or fundamentally alter a project’s viability.
Regime changes and shifts in governmental ideology or strategic priorities are typical flashpoints for political risk. What might begin as a change in leadership can evolve into a broader reorientation of policy, directly affecting the legal, regulatory, or economic frameworks that underpin infrastructure and energy developments.
Given the potential for political risk to undermine project economics and contractual stability, we encourage developers, investors, and contractors to address these issues proactively. While it is impossible to eliminate political risk entirely, there are contractual mechanisms and external protections–such as insurance and bilateral investment treaties (BITs)–that can mitigate its impact.
Change in Law provisions directly address a contract’s exposure to the legal and regulatory environment by defining the rights and obligations of the parties when new laws or regulatory changes affect the project.
Key considerations for the parties include:
Well-drafted Change in Law provisions provide for commercial predictability and a structured response to legal and regulatory changes that might otherwise affect the development or operation of a project.
A contract can apply a definition of "Force Majeure" that incorporates circumstances or consequences of political instability. Where unforeseen circumstances beyond a party’s control affect its performance of its obligations under the contract, the Force Majeure provisions should set out an appropriate framework for relief.
The parties should consider:
If a party’s role in the development or operation of the project becomes unviable (including a result of a Change in Law or circumstances constituting Force Majeure), that party may wish to terminate the contract (or contracts) and exit the project.
The parties must ensure that the termination provisions deal appropriately with the following:
Bespoke expropriation clauses: In higher-risk jurisdictions, it may be appropriate to include a specific expropriation clause setting out the consequences of any direct or indirect appropriation of assets by a sovereign state.
Currency: Where currency instability is a concern, the parties might consider pegging amounts payable under the contract to another currency. Project entities can also address inconvertibility risk with state-backed guarantees and insurance coverage.
Delay provisions: The Parties should consider their entitlements to claim for additional time and expenditure where supply chain delays, customs queues and other scheduling disruptions are likely to affect a project.
Indemnities: If the indemnities granted by the parties in respect of the project (such as indemnities in relation to people, property and pollution) are not fault-based, contract parties should exclude the consequences of state actions from the scope of their liabilities.
Relationship between provisions: Provisions addressing political risk should be clearly distinguished from one another. For example, there should be no duplication of reliefs across the Change in Law, Force Majeure and Abandonment provisions, or the Change in Control and Expropriation provisions.
Relationship between contracts: Many infrastructure projects involve complex contractual chains—such as head contracts and subcontracts. A disruption affecting one party (e.g., a subcontractor’s Force Majeure) should entitle the other party (e.g., the main contractor) to equivalent relief under the next contract in the chain. This “back-to-back” approach ensures consistent risk allocation across related agreements, avoiding gaps in entitlement or liability.
Mitigation: It might be appropriate for the parties to be required to mitigate the impacts of political or regulatory events before relying on the reliefs available under the Change in Law, Force Majeure or other provisions of the contract. The efforts required should be realistic and should be matters within the parties’ control (e.g., a party enforcing its rights under a concession agreement or government contract).
Local law restrictions: In some jurisdictions, there are local law restrictions on currency provisions, changes of control and divestment from infrastructure and energy projects. It is essential to consider how these might affect the operation and enforceability of contract provisions.
Political risk insurance (PRI) can provide coverage for loss of income and additional costs where contractual protections fall short. Policies can cover risks such as expropriation, currency inconvertibility, political violence, and breach of contract by a host government.
PRI policies commonly exclude economic risks (such as market downturns), war and known risks (such as pre-existing disputes). Parties should assess whether supplemental contingency coverage is appropriate for known risks identified during legal due diligence.
Bilateral investment treaties (BITs) offer foreign investors an effective legal remedy against discriminatory treatment and unlawful expropriation. There are thousands of BITs in force between different states, but some common standards imposed by BITs include a fair and equitable treatment standard and protection against unlawful expropriation.
Well-drafted contractual protections and strategic use of other tools, such as political risk insurance and investment treaties, play a critical role in managing political risk in energy and infrastructure projects.
Hogan Lovells can help sponsors, lenders and developers to tailor contract frameworks and dispute resolution strategies and to structure investments with key political risks in mind. We provide practical, cross-disciplinary support throughout the project lifecycle and our team has experience advising on projects in high-risk jurisdictions.
If you have any questions, please do not hesitate to get in touch with any of the key contacts listed, your usual Hogan Lovells contact, or click here to get in touch with a member of the Hogan Lovells energy team. For more Energy content, visit our interactive Energy Hub.
Authored by Johari Adjei.